Cabinet/012 Cabinet Dual Duct Units.pdf
Return to Procedures Main Menu
Index: Cabinet
Subject: (12) Dual Duct Units
Date: August 30, 2005
When designing replacement dual duct units, the hot deck and cold deck location within the Seasons-4 replacement unit MUST match orientation of the existing unit as shown on the field measurement drawings. If the field measurement drawings do not indicate the orientation of the hot deck and cold deck, the project engineer MUST get clarification from Sales before proceeding with the design of the equipment.
For new dual duct units, the project engineer may determine the orientation of the hot deck and cold deck ONLY when Sales verifies that the consulting engineer will be working from our design. If the project has been designed using another manufacturer’s equipment, the project engineer MUST match the orientation of the basis of design. If it is unclear whether or not the configuration has been determined by the consulting engineer, the project engineer MUST get clarification from Sales before proceeding with the design of the equipment.